STATE ENTERPRISES’ INVESTMENT PROGRAMME 2014
52
SUSTAINING GROWTH, SECURING PROSPERITY
• Acquisition of UPS units for North Terminal
– The acquisition entails the replacement of
malfunctioning/obsolete UPS units in the
Communications and server rooms in the
North Terminal. The estimated cost of the
project is $0.6 million.
• Link all AATT PBX systems using TSTT
Metro Ethernet Circuits
– This project aims
to reduce the recurring costs of intra-site
calls by installing internal routing calls among
the North Terminal, South Terminal and ANR
Robinson International Airport.The estimated
cost of the project is $0.5 million.
• Installation of Temperature/Humidity
Sensors in Communications and Server
Rooms
–This installationwill enableproactive
action to protect the information and
communications systems from the effects of
malfunctioning air-conditioning systems. The
estimated cost of the project is $0.3 million.
• Upgrade of BMS System at North Terminal
– The scope of works includes the supply and
installation of hardware devices and software
package to upgrade the existing BMS for the
air conditioning system. The estimated cost
of the project is $5.7 million.
• Fire Suppression for the North Terminal
Switch Room, South Terminal Substation
and Pump House
– This entails the supply
and installation of three (3) carbon dioxide fire
suppression systems for the North Terminal
Generator Room, South Terminal Generator
Room and Pump House Engine Room. The
estimated cost of the project is $1.0 million.
• UV System for the Sewer Treatment Plant
– The UV disinfection system facilitates the
decontamination of emissions from the sewer
treatment plant. This will result in an increase
of the overall FC reduction to the acceptable
relevant standards of 200/ml and below,
which complies with the EMA Standard for
Water Pollution, 2005. The estimated cost is
$0.6 million.
• Purchase of 60 feet Manlift
– The project
involves the purchase of a 60 feet manlift for
the maintenance of boarding bridges, lighting
systems and building repairs at the Piarco
International Airport. The estimated cost of
the project is $0.4 million.
• Fire Sprinklers at the North Terminal
Piarco International Airport
– This project
comprises the supply and installation of
3,300 new fire sprinklers for the entire North
Terminal. The estimated cost of the project is
$2.5 million.
ADMINISTRATION
URBAN DEVELOPMENT CORPORATION OF
TRINIDAD & TOBAGO LIMITED (UDeCOTT)
In achieving the GORTT’s objective to enhance
the quality of life for citizens and administer
municipal
development,
UDeCOTT
has
embarked on the construction of nine (9) police
stations in various locations, of which Guapo
Police Station was aborted at the design stage.
The initial estimated cost of this programme
was $445.6 million and was revised to $426.34
million. Projected expenditure of for fiscal 2013 is
$206.6million and for fiscal 2014 $121.39million.