73
210.
Infrastructure upgrade works implemented by Special Purposes State Enterprises
continued in various communities within Trinidad with expenditure totalling $452.4
million under the IDF.
211.
In the Laventille West, POS North/St Ann‟s West and POS South Constituencies,
community enhancement projects totalling approximately $30 million were implemented.
Completed works include construction of box drains, storm water drains and slipper
drains in Angelina Terrace, Never Dirty; Beetham Phase 5 and Mande Terrace, Belmont.
Expenditure for these initiatives was $0.3 million. Construction of designated garbage
collection points were completed at a cost of $0.2 million at Rosewood Avenue, Coconut
Drive; Desperlie Crescent, Laventille and Beverly Hills, John John.
212.
Infrastructure works on Laventille Road which comprised the construction of
retaining walls, widening of roadways to include kerbs, slipper and pavements was
completed with expenditure incurred in the amount of $5.4 million. Works in the
Morvant area comprised the renovation of the existing pavilion at Coconut Drive,
Morvant at a cost of $1 million which include the construction of new public toilets and
cafeteria and the construction of a retaining wall at Red Hill. Conceptual designs have
also been prepared to facilitate the establishment of a Homework Centre at Sea Lots.
Recreation Ground at Coconut Drive Morvant