Tamana Campus - continuation of construction work at the signature
building which is seventy-one per cent (71%) completed
O‟Meara Campus - equipment was purchased for Biomedical Engineering
Lab and repainting of the internal walls of the Academic Building has
commenced
Refurbished Computer Laboratory at John Donaldson Technical Institute
173.
Upgrades have continued to the Caribbean Union College and works have
continued on the development of the Tobago Technical School.
College of Science, Technology and Applied Arts of Trinidad and Tobago (COSTAATT)
174.
The College of Science, Technology and Applied Arts of Trinidad and Tobago
(COSTAATT) utilised $43.4 million for fiscal 2013.
175.
In preparation for the development of a Master Plan for COSTAATT, five (5)
Project management staff were recruited and internal stakeholder consultations to inform
the Master Plan were held at all campus sites. External stakeholder consultations with
regional corporations, chambers of commerce and relevant NGOs are to be undertaken.
Several activities were undertaken for construction of the new COSTAAT campus at
Chaguanas including the preparation of the request for proposal for design and
construction project management consultancy services as well as the completion of the
user/design brief.