residential and economic development for a stable and reliable supply. Activities
undertaken during the fiscal year included:
completion of two (2) Overhead Lines - Mt Pleasant/Diamond Vale 66 kV
Overhead line (4.7 km) and the Carenage/Mt Pleasant 66 kV Overhead line
(5.5 km) with the Debe/Penal 132 kV tower line (12 km) being ninety-eight
per cent (98%) completed and the Cove/Milford Bay #2 66 kV Circuits-
Phase I - Cable Section having ninety per cent (90%) completion
completion of two (2) Tower Lines - Bamboo/Mt hope 132 kV tower line
(3.6 km) and San Rafael/Wallerfield 132 kV tower Line (10 km) with
surveys completed for establishment of four (4) Tower Lines - Pinto
Road/Wallerfield Tower line (7.2 km), Reform/Debe 220 kV tower line
(12.5 km), Debe/Union 220 kV tower line (22.5 km) and Bamboo/East Dry
River 132 kV Tower Line ( 11 km)
progression of works at four (4) substations: Pinto Road 66 kV Substation –
overall seventy-five per cent (75%) completed.; St James Substation -
overall ten per cent (10%) completed; Gateway 132/33 kV Substation -
overall eighty-seven per cent (87%) completed and Milford Bay Crown
Point, Tobago 66/33/12 kv Sub-Station having sixty per cent (60%) overall
completion
completion of Cable circuits at Brechin Castle/Reform #1 & #2 220 kV
circuits with three (3) cable circuits at Gateway Substation eight per cent
(8%) completed and the Sealots/Gateway 132 kV cable circuit overall sixty-
three (63%) completed.
112.
The Tobago House of Assembly received an allocation of $0.5 million for Street
Lighting throughout Tobago. This amount was expended on works to Mt. Pleasant Local
Road, Bethesda Road, Dunveygon Road, and Store Bay Local Road which entailed
upgrades from 75W to 150W streetlights and also at Carnbee #1 which had an upgrade
from 150W to 250W.
The Arts and Multiculturalism
113.
An allocation of $2 million was provided in fiscal 2013 for the refurbishment of
Queen‟s Hall. The entire allocation was utilised and the following activities were
undertaken:
purchase and installation of one (1) Dual Circuit Chiller and one (1) Air
Separator
upgrade of the orchestra pit lift, main theatre curtain system and the audio
system
114.
The amount allocated to the project for the Establishment of a Heritage Site at
Nelson Island was revised upwards from an allocation of $2 million to $5.24 million.