STATE ENTERPRISES’ INVESTMENT PROGRAMME 2014
92
SUSTAINING GROWTH, SECURING PROSPERITY
PROGRAMMES
ESTIMATED
TOTAL COST OF
PROGRAMME
TT$ million
ACTUAL
EXPENDITURE
TT$ million
PROJECTED
EXPENDITURE
TT$ million
DETAILS OF PROGRAMMES FOR 2014
OCT. 2011 TO
SEPT. 2012
OCT 2012 TO
MARCH 2013
APRIL TO
SEPT 2013
OCT 2013 TO
SEPT 2014
Health
URBAN DEVELOPMENT CORPORATION OF TRINIDAD AND TOBAGO (UDeCOTT)
Funded by GORTT Serviced Loan
Penal Hospital
1,840.16
0.26
0.03
214.53
562.65
Site hoarding and preliminary
preparatory works to take place prior to
start of the full construction works.
Couva
Children's
Hospital &
UWI School of
Medicine and
Nursing
1,520.92
1.58
12.95
331.91
255.16
Site development work in progress.
GORTT
Serviced Loan
3,361.08
1.84
12.98
546.44 817.81
Total –
UDeCOTT
3,361.08
1.84
12.98
546.44 817.81
Total – Health 3,361.08
1.84
12.98
546.44 817.81