STATE ENTERPRISES’ INVESTMENT PROGRAMME 2014
74
SUSTAINING GROWTH, SECURING PROSPERITY
PROGRAMMES
ESTIMATED
TOTAL COST OF
PROGRAMME
TT$ million
ACTUAL
EXPENDITURE
TT$ million
PROJECTED
EXPENDITURE
TT$ million
DETAILS OF PROGRAMMES FOR 2014
OCT. 2011 TO
SEPT. 2012
OCT 2012 TO
MARCH 2013
APRIL TO
SEPT 2013
OCT 2013 TO
SEPT 2014
TRINIDAD AND TOBAGO NATIONAL PETROLEUM MARKETING COMPANY LIMITED (NP)
Funded by Retained Earnings
Upgrade of
Dealer Sites
(full and partial
upgrade)
288.91
4.33
5.30
37.40
223.74
Project entails the full upgrade of
twenty-three (23) Service Stations. The
full upgrade of the Siparia and D’Abadie
Service Stations was completed in
December 2012. The others are due for
completion by 2014 and 2015.
Installation of
eight (8) CNG
dispensers
2.04
0.00
0.00
2.04
0.00
The installation of eight (8) CNG
dispensers to replace obsolete
dispensers in the Service Station
Network is expected to be completed by
November 2013.
Construction
of two (2) New
CNG Service
Stations at
VMCOTT and
PTSC Terminals
Port of Spain.
33.00
0.00
0.00
6.60
26.40
Construction of CNG facility at PTSC
to commence in September 2013 and
completion is expected by April 2014.
Construction of
Fuel Tank at La
Brea Industrial
Development
Co. Ltd
(LABIDCO)
and 9,000 bbl
GasOil Tank in
Tobago.
4.60
2.63
2.00
0.97
0.50
Construction of Gas Oil Storage Tank in
La Brea has not started. The 9,000 bbl
GasOil Tank in Tobago is completed and
is awaiting approvals from the MEEA.